The existing water lines and service lines will remain in service while the new water main is being constructed. After the new main is tested and accepted, the connections will be made to the existing system and the existing service lines will be replaced and transferred to the new main. On street parking will be affected as the project progresses. B-T Construction was the successful bidder. The new line will be up sized from 4” cast iron pipe to 8” PVC lines. Detail Map